Theatre auditorium seating at the centre of a refurbishment programme
Case Studies

Programmes delivered for venues like yours

Refurbishment, installation and modernisation programmes for theatres, universities and council facilities. Each one started with a survey and finished with a documented handover.

Selected Programmes

Challenge, solution, outcome

Representative programme summaries showing the scope, the constraints and the result. References are available on request during tender.

Heritage theatre auditorium with refurbished burgundy velvet seating
Theatre · Grade II ListedWest London

Heritage Theatre Auditorium Refurbishment

A producing theatre with an auditorium last refurbished in the 1990s, seating that failed on comfort and appearance, and a nine-week dark period in which all works had to be completed.

Challenge
Original cast-iron frames were sound, but fabric was faded and torn across the stalls and dress circle, foam had collapsed, and a large number of armrests and end panels were damaged. Listing conditions prohibited any change to the visible frame or fixings.
Solution
Every frame was retained and stripped in situ by a specialist fitting team. Fabric was matched to an archive sample and tested for flame performance, foam was replaced to original profiles, and armrests and aisle panels were repaired or remade off site. Works were phased stalls first, then circle, within the dark period.
Outcome
The auditorium reopened on schedule with a consistent, like-new house, no change to capacity or listed fabric, and a seating asset expected to serve a further 12–15 years before replacement is revisited.

642

Seats refurbished

9 weeks

Dark period programme

48%

Saved vs replacement

Tiered university lecture theatre with newly installed seating
UniversityHome Counties

University Lecture Theatre Upgrade

A 420-seat tiered lecture theatre with failing step lighting, poor accessibility provision and seating that no longer met the university's fire and comfort standards.

Challenge
The theatre is timetabled continuously through term. Only the eight-week summer vacation was available, and the university needed additional wheelchair and companion places without falling below its target capacity.
Solution
We surveyed and modelled the room, then re-planned the rear tiers to add dispersed wheelchair bays with companion seats alongside, reclaiming space lost to an oversized projection position. Seating was ordered in advance of the window, delivered in phases and installed in seven weeks with commissioning completed inside the vacation.
Outcome
Capacity was maintained, accessible provision increased from two to six dispersed places with improved sightlines, and the theatre reopened on the first day of term with full handover documentation.

420

Seats replaced

7 weeks

Installation window

6

Accessible places added

Modern retractable seating bank in a multipurpose sports hall
Leisure · Dual UseSouth East London

Retractable Seating Modernisation

A council-run sports hall with a 1990s retractable bank that had failed twice in a season, with no spares support from the original manufacturer.

Challenge
The bank was slow to deploy, jamming on the lower rows, and safety interlocks were unreliable. Replacement of the whole system was quoted at a level the capital programme could not support.
Solution
Our engineers surveyed the structure, drive and guide rails, then rebuilt the mechanism with modern wheels, bearings and limit switches, replaced damaged seats and re-upholstered the seating, and upgraded the control system. Works were completed in two short closures during the summer programme.
Outcome
Deployment time reduced from 25 minutes to under 6, breakdowns eliminated across the following season, and the council avoided full replacement — while receiving a documented maintenance plan for the asset going forward.

8 rows

Mechanism rebuilt

60%

Saved vs full replacement

48 hrs

Maintenance response

Next Step

Discuss a programme like these

Send us the constraints you are working within — dark periods, term dates, budgets or listed interiors — and we will tell you honestly what is achievable.

    base44
    Edit with Base44